19 December 2023
On December 15 and 18, 2023, two 110 kV substations were opened:
In total, five 35-110 kV substations were built and reconstructed in the Minsk energy system in 2023, and another 6 are under construction. Work on modernizing power grids also continues: 640 km will be modernized in 2023. In total, more than 2.1 thousand km were built and modernized throughout the country in 11 months of 2023. It is planned that 3 thousand km will be modernized in 2024.
The creation and modernization of energy sources, increasing the country’s energy efficiency makes an important contribution to the achievement by the Republic of Belarus of Sustainable Development Goals 7, 9, 11 and other SDGs.